Master Schedule

Field Survey

Summer & Fall 2015

Stream & Precipitation Monitoring

Summer & Fall 2015

Model Development & Analysis

Winter 2015 & Spring 2016

Present Possible Solutions to City

Summer 2016

Progress Updates

Data Collection

Data Collection

  • Community Meetings were held on October 22 and October 29, 2015

  • Many residents have submitted surveys. Thank you! A mailing will be sent to residents who have expressed concerns at public meetings but have not yet submitted a survey 

  • Stream and rain gauges installed on June 6, 2015
Field Survey

Field Survey

  • Channel and Ditch Data - 90%

  • Inlets and Drain Manholes - 70%

Model

Model

  • We are creating the pipe network as the surveyors collect & download data. Model Development began in December 2015